Important update for Garve to Aultguish - from BTO - Broadband Self Digs

in Broadband Group by Lucy Beattie
The deadline for Garve to Aultguish self-digs is Friday 10th August. If your property is in this area, please note the new completion dates!
July update from BTO
July update frpm BTO

Check the BTO update (under Network 2), Garve to Aultguish is particularly important to those who are undertaking self digs. The deadline for completion is Friday 10th August - as outlined in the above schedule:

Activities in Progress

  • Surveys and detailed planning – Completed
  • Spine fibre – Ongoing
  • Spine build between Inchbae & Aultguish progressing. Traffic management is required along the remaining road to complete the spine.
  • Local fibre build work – Ongoing
  • Fibre jointing with spine and local infrastructure has started
  • Two sites for poling/civils work require discussions with the Forestry Commission – discussions continue
  • DYO build – ongoing, all customers except the two sites mentioned above now have equipment and know where build to
  • Network commissioning and auditing – planning started

We plan to start commissioning work in August. In order for that to happen all DYO’s must be completed by Friday 10th August

Questions & Comments

There hasn't been any comments yet, why not be the first?

Have your say...

(your answer proves you are a person)

Please note, comments are checked before appearing on the site.

top